  • Buckhannon Water Treatment Plant Improvements; Buckhannon, WV

  • Buckhannon Water Treatment Plant Improvements; Buckhannon, WV

  • Buckhannon Water Treatment Plant Improvements; Buckhannon, WV

The City of Buckhannon recognized their water treatment plant was at the end of its useful life and began making improvements in 2016. This valuable asset produces approximately 2 Million Gallons per Day (MGD) of safe drinking water to customers within the City of Buckhannon's service area. The project included all new flocculation and sedimentation equipment, new valves and actuators, concrete rehabilitation, replacement of filter media, and other miscellaneous improvements. The project was completed in 2017 at a total project cost of $1.9 Million.